GREY ZONE - Dubai

Opened 2026-01-08 · owner Gilles · First live GREY ZONE venue. Full fitout + installation. Imported from "GREY ZONE" tab of New museum CHECKLIST and timings.

76tasks shown
71active
53overdue
Reset
Task Active stage Snooze Active-stage commit Done Template Supplier
needs dates
Winterplus Install on site
2026-06-05 -48d ⚠ needs commit 2/6 simple
at risk
Gilles Search for options
2026-06-09 -44d 2026-06-05 -48 0/6 sourcing
at risk
Gilles finalize design see here https://docs.google.com/spreadsheets/d/1wPlCYqVcRjEOlI9JBhz4ZGOjIa_9m4zdcICXMYGHkeo/edit?gid=1559200318#gid=1559200318
2026-06-18 -35d 2026-06-25 -28 0/3 simple
at risk
Winterplus draw and create door gaps conceilings (left
2026-06-25 -28d 2026-01-12 -192 0/8 sourcing Oredy + Fisher Yu
at risk
Winterplus Get DEWA upgrade
2026-06-25 -28d 2026-01-17 -187 0/2 simple
at risk
Winterplus Make all
2026-06-25 -28d 2026-01-27 -177 0/1 simple
at risk
Winterplus install
2026-06-25 -28d 2026-01-27 -177 0/1 sourcing
at risk
Noby order another proto from Joey
2026-06-25 -28d 2026-01-28 -176 0/5 sourcing Joey
at risk
Winterplus install wall moldings
2026-06-25 -28d 2026-01-30 -174 0/3 sourcing
at risk
Gilles test cnc sample from Shyam
2026-06-25 -28d 2026-02-01 -172 0/4 sourcing
at risk
Alaa Test the RJ45 adater with Alaa with buttons (the USB adapter is fine!)
2026-06-25 -28d 2026-02-04 -169 0/2 sourcing
at risk
Alaa Receive pcbs from JLCPCB
2026-06-25 -28d 2026-02-04 -169 0/3 sourcing Peter + ...
at risk
Gilles Pass by Creative Minds to find the postcard tones and see a little bit of everything.
2026-06-25 -28d 2026-02-04 -169 0/1 simple
at risk
Gilles Make 10 boxes mass prod
2026-06-25 -28d 2026-02-05 -168 0/5 sourcing
at risk
Gilles check
2026-06-25 -28d 2026-02-05 -168 0/2 sourcing Sam
at risk
Winterplus Receive
2026-06-25 -28d 2026-02-05 -168 0/2 sourcing
at risk
Gilles Ship
2026-06-25 -28d 2026-02-06 -167 0/1 sourcing
at risk
Gilles Ship
2026-06-25 -28d 2026-02-06 -167 0/2 sourcing
at risk
Gilles Have Grace shrink the metal tile a little bit
2026-06-25 -28d 2026-02-06 -167 0/2 sourcing Grace CAO
at risk
Elaiza receive samples from other suppliers with better absorbance
2026-06-25 -28d 2026-02-07 -166 0/4 sourcing
at risk
Gilles Receive Tender process from Elaiza
2026-06-25 -28d 2026-02-08 -165 0/1 sourcing
at risk
Gilles Receive Tender process from Elaiza
2026-06-25 -28d 2026-02-08 -165 0/1 sourcing
at risk
Gilles Lower the mushroom by 1 or 1.5 mm
2026-06-25 -28d 2026-02-10 -163 0/3 sourcing Victor
at risk
Noby get feedback from Noby
2026-06-25 -28d 2026-02-10 -163 0/1 simple
at risk
Gilles Prepare a testing Pi (like the pi-39 but maybe a clone ?)
2026-06-25 -28d 2026-02-10 -163 0/9 sourcing Nicole Lu
at risk
Noby receive 2nd proto
2026-06-25 -28d 2026-02-10 -163 0/3 sourcing Peter
at risk
Elaiza Ship sofa of Ben Evergo (feb12)
2026-06-25 -28d 2026-02-12 -161 0/2 sourcing Ben Evergo + Poesi
at risk
Noby oder from Nicole
2026-06-25 -28d 2026-02-13 -160 0/3 sourcing
at risk
Rabi Paint and Install the LED skirtings we made
2026-06-25 -28d 2026-02-14 -159 0/2 sourcing
at risk
Gilles Test the models from China
2026-06-25 -28d 2026-02-14 -159 0/8 sourcing Clancy Chan
at risk
Alaa Get Alaa the proto from China (Elaiza) for prod
2026-06-25 -28d 2026-02-15 -158 0/1 simple
at risk
Gilles order big quantity
2026-06-25 -28d 2026-02-15 -158 0/2 sourcing
at risk
Gilles try the received box
2026-06-25 -28d 2026-02-15 -158 0/4 sourcing
at risk
Gilles Install (see here)
2026-06-25 -28d 2026-02-15 -158 0/1 sourcing
at risk
Winterplus do
2026-06-25 -28d 2026-02-15 -158 0/1 simple
at risk
Gilles design see here
2026-06-25 -28d 2026-02-16 -157 0/3 simple Sam
at risk
Gilles Ship chinese PCB samples to Alaa
2026-06-25 -28d 2026-02-16 -157 0/2 sourcing JCL- ELLE
at risk
Gilles develop a few games
2026-06-25 -28d 2026-02-19 -154 0/2 simple
at risk
Winterplus pull the cables to the gamehub
2026-06-25 -28d 2026-02-20 -153 0/1 simple
at risk
Gilles design see here
2026-06-25 -28d 2026-02-20 -153 0/4 simple
at risk
Gilles Ship the screens
2026-06-25 -28d 2026-02-20 -153 0/1 sourcing Sandra Duan
at risk
Gilles Ship 55 pcs
2026-06-25 -28d 2026-02-20 -153 0/1 sourcing Yixin Zhou
at risk
Elaiza Receive samples from China
2026-06-25 -28d 2026-02-23 -150 0/5 sourcing
at risk
Gilles code
2026-06-25 -28d 2026-02-25 -148 0/4 sourcing
at risk
Gilles arrived
2026-06-25 -28d 2026-02-25 -148 0/2 sourcing
at risk
Gilles install in final enclosure
2026-06-25 -28d 2026-02-28 -145 0/1 sourcing Damon Lin
at risk
Gilles install all
2026-06-25 -28d 2026-03-01 -144 0/1 sourcing
at risk
Gilles confirm prod
2026-06-25 -28d 2026-03-12 -133 0/2 sourcing Wendy
at risk
Gilles test
2026-06-25 -28d 2026-04-01 -113 0/2 sourcing Luke Lu
Start running cables everywhere
2026-06-25 -28d 1/2 renovation
needs dates
Gilles Install
2026-06-25 -28d 1/3 simple
Prepare all provisions (Elec + Data)
2026-06-25 -28d max finish 17 Oct 1/7 simple
Winterplus Make final version
2026-07-26 3d 1/3 simple
Gilles Choose model
2026-07-27 4d 0/4 sourcing Polly Yang
at risk
⚠ assign produce
2026-07-30 7d ⚠ needs commit 1/7 sourcing
at risk
⚠ assign produce
2026-07-30 7d ⚠ needs commit 1/7 sourcing
at risk
⚠ assign order
2026-07-30 7d ⚠ needs commit 0/7 sourcing Dimonk
needs dates
Gilles Study howto integrate with Elevenlabs-nodejs api
2026-07-30 7d ⚠ needs commit 0/1 simple
needs dates
Noby make a printable version of the models found online
2026-07-30 7d ⚠ needs commit 0/1 simple
needs dates
Gilles have them installed by WP
2026-07-30 7d ⚠ needs commit 0/1 sourcing
needs dates
Gilles winterplus will do
2026-07-30 7d ⚠ needs commit 0/1 simple
needs dates
Eva Make sure they did the small holes aswell
2026-07-30 7d ⚠ needs commit 0/1 simple
needs dates
⚠ assign Get DM Approval
2026-07-30 7d ⚠ needs commit 0/1 simple
needs dates
Eva redo pavement
2026-07-30 7d ⚠ needs commit 0/1 simple
needs dates
⚠ assign received
2026-07-30 7d ⚠ needs commit 0/1 sourcing
needs dates
Elaiza done. shipping to Brussels
2026-07-30 7d ⚠ needs commit 0/1 sourcing Nicole Lu
needs dates
Gilles decide ?
2026-10-17 86d ⚠ needs commit max finish 17 Oct 0/4 simple
needs dates
Gilles decide later > design see here
2026-10-17 86d ⚠ needs commit max finish 27 Oct 0/3 simple
needs dates
Gilles design see here
2026-10-17 86d ⚠ needs commit max finish 27 Oct 0/3 simple
needs dates
Gilles design see here
2026-10-17 86d ⚠ needs commit max finish 27 Oct 0/3 simple
needs dates
Gilles design see here
2026-10-17 86d ⚠ needs commit max finish 27 Oct 0/3 simple
Touchscreens @@office
2026-02-20 -153d 2/2 sourcing Sophia Chen
at risk
2/7 simple
0/5 simple Peter
0/1 simple
0/1 simple